Solar plant: site data

Solar power plant in Tuzly, Mykolaivskyi Raion, Mykolaiv Oblast

Tuzly: 1,285 kWh per kWp a year, tilt 37° 1° east of south (PVGIS). 7.2% above the oblast median (1,198). #23 of 238 in the rayon, #23 of 909 in the oblast.

Mykolayiv, the rayon centre, is 56 km away. 4 m above sea level. 17 km away: Berezanka, the nearest bigger centre, 1,260 — 1.9% more here. Snow and wind from the nearest regional centre in the DBN — Одеса, 55 km. 9.60 m between rows, pitch 13.42 m (latitude 46.7°).

Yield of 1 kWp
1,285kWh/year
Tilt
37°1° east of south
10 kW
12,847kWh/year
Row pitch
13.42m · GCR 0.36
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
880 / 460Pa

Ground frame designer

A ground frame for a solar plant: Tuzly

The designer opens with this place’s coordinates, latitude 46.7° for the row spacing and the DBN loads of the nearest regional centre — Одеса, 55 km: snow 880 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

48Jan64Feb110Mar132Apr148May146Jun155Jul153Aug130Sep102Oct55Nov40Dec

July: 155 kWh/kWp, December: 40 — 3.9 times less.

January: 48 against 38 in the oblast, 26.3% more.

Tuzly: plants, kWh
kWpA yearJulyDecember
56,424775200
1012,8471,550400
1519,2712,325600

Snow and wind: Одеса

Example: a 10 kW ground frame

For the loads of Odesa: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Mykolaivskyi RaionMykolaiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.