Solar plant: site data

Solar power plant in Shevchenko, Voznesenskyi Raion, Mykolaiv Oblast

Shevchenko: 1,195 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). Exactly the oblast median (1,198). #94 of 252 in the rayon, #495 of 909 in the oblast.

Voznesensk, the rayon centre, is 24 km away. 103 m above sea level. 24 km away: Voznesensk, the nearest bigger centre, the same 1,192. Snow and wind from the nearest regional centre in the DBN — Миколаїв, 70 km. 9.91 m between rows, pitch 13.78 m (latitude 47.6°).

Yield of 1 kWp
1,195kWh/year
Tilt
36°3° east of south
10 kW
11,946kWh/year
Row pitch
13.78m · GCR 0.35
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
870 / 470Pa

Ground frame designer

A ground frame for a solar plant: Shevchenko

The designer opens with this place’s coordinates, latitude 47.6° for the row spacing and the DBN loads of the nearest regional centre — Миколаїв, 70 km: snow 870 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan54Feb100Mar123Apr139May141Jun152Jul148Aug124Sep96Oct48Nov33Dec

July: 152 kWh/kWp, December: 33 — 4.6 times less.

January: 37 against 38 in the oblast, 2.6% less.

Shevchenko: plants, kWh
kWpA yearJulyDecember
55,973760165
1011,9461,520330
1517,9192,280495

Snow and wind: Миколаїв

Example: a 10 kW ground frame

For the loads of Mykolaiv: 11.16 kWp, 18 panels, 372 kg of steel, 14 piles, materials ≈ 50,842 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Voznesenskyi RaionMykolaiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.