Solar plant: site data
Solar power plant in Kavkaz, Bashtanskyi Raion, Mykolaiv Oblast
Kavkaz: 1,214 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 1.4% above the oblast median (1,198). #82 of 279 in the rayon, #296 of 909 in the oblast.
Novyi Buh, the rayon centre, is 61 km away. 67 m above sea level. 17 km away: Bereznehuvate, the nearest bigger centre, the same 1,216. Snow and wind from the nearest regional centre in the DBN — Херсон, 80 km. 9.74 m between rows, pitch 13.61 m (latitude 47.3°).
- Yield of 1 kWp
- 1,214kWh/year
- Tilt
- 36°3° east of south
- 10 kW
- 12,144kWh/year
- Row pitch
- 13.61m · GCR 0.35
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 760 / 480Pa
Ground frame designer
A ground frame for a solar plant: Kavkaz
The designer opens with this place’s coordinates, latitude 47.3° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 80 km: snow 760 Pa, wind 480 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 152 kWh/kWp, December: 34 — 4.5 times less.
November: 50 against 48 in the oblast, 4.2% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 6,072 | 760 | 170 |
| 10 | 12,144 | 1,520 | 340 |
| 15 | 18,216 | 2,280 | 510 |
Example: a 10 kW ground frame
For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.
How these numbers are computed
Nearby
- Novorosiyske2 km1,213 kWh/kWp
- Lepetykha5 km1,208 kWh/kWp
- Murakhivka6 km1,223 kWh/kWp
- Ternovyi Yar7 km1,208 kWh/kWp
- Tokareve7 km1,219 kWh/kWp
- Velyke Artakove7 km1,216 kWh/kWp
All places: Bashtanskyi RaionMykolaiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.