Solar plant: site data

Solar power plant in Rusyn, Sheptytskyi Raion, Lviv Oblast

Rusyn: 1,101 kWh per kWp a year, tilt 38° 2° east of south (PVGIS). 1.6% above the oblast median (1,084). #8 of 207 in the rayon, #23 of 1532 in the oblast.

Sheptytskyi, the rayon centre, is 15 km away. 224 m above sea level. 15 km away: Sheptytskyi, the nearest bigger centre, 1,079 — 2.1% more here. Snow and wind from the nearest regional centre in the DBN — Львів, 70 km. 12.83 m between rows, pitch 16.60 m (latitude 50.5°).

Yield of 1 kWp
1,101kWh/year
Tilt
38°2° east of south
10 kW
11,014kWh/year
Row pitch
16.60m · GCR 0.29
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,310 / 520Pa

Ground frame designer

A ground frame for a solar plant: Rusyn

The designer opens with this place’s coordinates, latitude 50.5° for the row spacing and the DBN loads of the nearest regional centre — Львів, 70 km: snow 1,310 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

35Jan53Feb98Mar118Apr129May134Jun135Jul133Aug109Sep85Oct42Nov31Dec

July: 135 kWh/kWp, December: 31 — 4.4 times less.

January: 35 against 39 in the oblast, 10.3% less.

Rusyn: plants, kWh
kWpA yearJulyDecember
55,507675155
1011,0141,350310
1516,5212,025465

Snow and wind: Львів

Example: a 10 kW ground frame

For the loads of Lviv: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Sheptytskyi RaionLviv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.