Solar plant: site data
Solar power plant in Shubino, Feodosiiskyi Raion, Autonomous Republic of Crimea
Shubino: 1,292 kWh per kWp a year, tilt 35° 2° west of south (PVGIS). 0.6% above the oblast median (1,284). #27 of 113 in the rayon, #439 of 1025 in the oblast.
Feodosiya, the rayon centre, is 30 km away. 14 m above sea level. 5 km away: Islyam-Terek, the nearest bigger centre, the same 1,293. Snow and wind from the nearest regional centre in the DBN — Херсон, 251 km. 8.38 m between rows, pitch 12.30 m (latitude 45.3°).
- Yield of 1 kWp
- 1,292kWh/year
- Tilt
- 35°2° west of south
- 10 kW
- 12,915kWh/year
- Row pitch
- 12.30m · GCR 0.39
- T_min
- -27 °Cregion V, Crimean Mountains
- Snow S₀ / wind W₀
- 760 / 480Pa
Ground frame designer
A ground frame for a solar plant: Shubino
The designer opens with this place’s coordinates, latitude 45.3° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 251 km: snow 760 Pa, wind 480 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
August: 160 kWh/kWp, January: 44 — 3.6 times less.
January: 44 against 47 in the oblast, 6.4% less.
| kWp | A year | August | January |
|---|---|---|---|
| 5 | 6,458 | 800 | 220 |
| 10 | 12,915 | 1,600 | 440 |
| 15 | 19,373 | 2,400 | 660 |
Example: a 10 kW ground frame
For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.
How these numbers are computed
Nearby
- Sinitsyno5 km1,285 kWh/kWp
- Tokarevo5 km1,289 kWh/kWp
- Islyam-Terek5 km1,293 kWh/kWp
- Sofiyevka7 km1,283 kWh/kWp
- Yarkoye Pole8 km1,293 kWh/kWp
- Krasnovka8 km1,285 kWh/kWp
All places: Feodosiiskyi RaionAutonomous Republic of Crimea: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.