Solar plant: site data

Solar power plant in Muromskoye, Bilohirskyi Raion, Autonomous Republic of Crimea

Muromskoye: 1,251 kWh per kWp a year, tilt 35° 2° east of south (PVGIS). 2.5% below the oblast median (1,284). #93 of 139 in the rayon, #951 of 1025 in the oblast.

Bilohirsk, the rayon centre, is 20 km away. 209 m above sea level. 20 km away: Bilohirsk, the nearest bigger centre, 1,261 — 0.8% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 244 km. 8.29 m between rows, pitch 12.21 m (latitude 45.1°).

Yield of 1 kWp
1,251kWh/year
Tilt
35°2° east of south
10 kW
12,513kWh/year
Row pitch
12.21m · GCR 0.39
T_min
-27 °Cregion V, Crimean Mountains
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Muromskoye

The designer opens with this place’s coordinates, latitude 45.1° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 244 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

50Jan64Feb99Mar125Apr140May140Jun149Jul152Aug126Sep96Oct64Nov48Dec

August: 152 kWh/kWp, December: 48 — 3.2 times less.

December: 48 against 45 in the oblast, 6.7% more.

Muromskoye: plants, kWh
kWpA yearAugustDecember
56,257760240
1012,5131,520480
1518,7702,280720

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Bilohirskyi RaionAutonomous Republic of Crimea: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.