Solar plant: site data
Solar power plant in Kalinino, Kurmanskyi Raion, Autonomous Republic of Crimea
Kalinino: 1,285 kWh per kWp a year, tilt 35° 1° west of south (PVGIS). Exactly the oblast median (1,284). #6 of 126 in the rayon, #505 of 1025 in the oblast.
Kurman, the rayon centre, is 49 km away. 19 m above sea level. 22 km away: Rozdolne, the nearest bigger centre, 1,319 — 2.6% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 134 km. 8.62 m between rows, pitch 12.54 m (latitude 45.7°).
- Yield of 1 kWp
- 1,285kWh/year
- Tilt
- 35°1° west of south
- 10 kW
- 12,848kWh/year
- Row pitch
- 12.54m · GCR 0.38
- T_min
- -27 °Cregion V, Crimean Mountains
- Snow S₀ / wind W₀
- 760 / 480Pa
Ground frame designer
A ground frame for a solar plant: Kalinino
The designer opens with this place’s coordinates, latitude 45.7° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 134 km: snow 760 Pa, wind 480 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 157 kWh/kWp, December: 42 — 3.7 times less.
February: 59 against 64 in the oblast, 7.8% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 6,424 | 785 | 210 |
| 10 | 12,848 | 1,570 | 420 |
| 15 | 19,272 | 2,355 | 630 |
Example: a 10 kW ground frame
For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.
How these numbers are computed
Nearby
- Matveyevka3 km1,283 kWh/kWp
- Levitanovka4 km1,282 kWh/kWp
- Ogorodnoye6 km1,299 kWh/kWp
- Traktovoye7 km1,296 kWh/kWp
- Pervomayske7 km1,279 kWh/kWp
- Pravda7 km1,291 kWh/kWp
All places: Kurmanskyi RaionAutonomous Republic of Crimea: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.