Solar plant: site data

Solar power plant in Filatovka, Perekopskyi Raion, Autonomous Republic of Crimea

Filatovka: 1,318 kWh per kWp a year, tilt 36° 1° west of south (PVGIS). 2.7% above the oblast median (1,284). #17 of 84 in the rayon, #213 of 1025 in the oblast.

Yany Kapu, the rayon centre, is 14 km away. 10 m above sea level. 8 km away: Armyansk, the nearest bigger centre, the same 1,317. Snow and wind from the nearest regional centre in the DBN — Херсон, 109 km. 9.02 m between rows, pitch 12.89 m (latitude 46.1°).

Yield of 1 kWp
1,318kWh/year
Tilt
36°1° west of south
10 kW
13,184kWh/year
Row pitch
12.89m · GCR 0.37
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Filatovka

The designer opens with this place’s coordinates, latitude 46.1° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 109 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

51Jan66Feb111Mar133Apr152May148Jun160Jul159Aug135Sep102Oct59Nov43Dec

July: 160 kWh/kWp, December: 43 — 3.7 times less.

January: 51 against 47 in the oblast, 8.5% more.

Filatovka: plants, kWh
kWpA yearJulyDecember
56,592800215
1013,1841,600430
1519,7762,400645

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Perekopskyi RaionAutonomous Republic of Crimea: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.