Solar plant: site data
Solar power plant in Bogatoye Ushchelye, Bakhchysaraiskyi Raion, Autonomous Republic of Crimea
Bogatoye Ushchelye: 1,280 kWh per kWp a year, tilt 36° 11° east of south (PVGIS). Exactly the oblast median (1,284). #69 of 85 in the rayon, #562 of 1025 in the oblast.
Bakhchysaray, the rayon centre, is 22 km away. 319 m above sea level. 22 km away: Bakhchysaray, the nearest bigger centre, 1,320 — 3.0% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 251 km. 8.24 m between rows, pitch 12.11 m (latitude 44.6°).
- Yield of 1 kWp
- 1,280kWh/year
- Tilt
- 36°11° east of south
- 10 kW
- 12,801kWh/year
- Row pitch
- 12.11m · GCR 0.40
- T_min
- -20 °Cregion IV, Southern coast of Crimea
- Snow S₀ / wind W₀
- 760 / 480Pa
Ground frame designer
A ground frame for a solar plant: Bogatoye Ushchelye
The designer opens with this place’s coordinates, latitude 44.6° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 251 km: snow 760 Pa, wind 480 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 151 kWh/kWp, December: 50 — 3.0 times less.
November: 70 against 63 in the oblast, 11.1% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 6,401 | 755 | 250 |
| 10 | 12,801 | 1,510 | 500 |
| 15 | 19,202 | 2,265 | 750 |
Example: a 10 kW ground frame
For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.
How these numbers are computed
Nearby
- Putylivka2 km1,291 kWh/kWp
- Poliana2 km1,232 kWh/kWp
- Novopolye3 km1,283 kWh/kWp
- Golubinka5 km1,283 kWh/kWp
- Nizhnaya Golubinka5 km1,282 kWh/kWp
- Novoulyanovka6 km1,293 kWh/kWp
All places: Bakhchysaraiskyi RaionAutonomous Republic of Crimea: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.