Solar plant: site data

Solar power plant in Pravdyne, Khersonskyi Raion, Kherson Oblast

Pravdyne: 1,270 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 1.3% above the oblast median (1,253). #42 of 109 in the rayon, #228 of 711 in the oblast.

Kherson, the rayon centre, is 33 km away. 40 m above sea level. 22 km away: Bilozerka, the nearest bigger centre, 1,286 — 1.2% less here. Snow and wind from the nearest regional centre in the DBN — Миколаїв, 31 km. 9.62 m between rows, pitch 13.44 m (latitude 46.7°).

Yield of 1 kWp
1,270kWh/year
Tilt
37°2° east of south
10 kW
12,699kWh/year
Row pitch
13.44m · GCR 0.36
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
870 / 470Pa

Ground frame designer

A ground frame for a solar plant: Pravdyne

The designer opens with this place’s coordinates, latitude 46.7° for the row spacing and the DBN loads of the nearest regional centre — Миколаїв, 31 km: snow 870 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

45Jan64Feb109Mar131Apr144May144Jun153Jul153Aug131Sep101Oct56Nov39Dec

July: 153 kWh/kWp, December: 39 — 3.9 times less.

February: 64 against 60 in the oblast, 6.7% more.

Pravdyne: plants, kWh
kWpA yearJulyDecember
56,350765195
1012,6991,530390
1519,0492,295585

Snow and wind: Миколаїв

Example: a 10 kW ground frame

For the loads of Mykolaiv: 11.16 kWp, 18 panels, 372 kg of steel, 14 piles, materials ≈ 50,842 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khersonskyi RaionKherson Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.