Spain: solar plant site data

Solar power plant in Lugo, Spain: yield, tilt angle and row spacing

Lugo: 1,314 kWh per kWp a year at the optimal tilt of 35°, 10° west of south (PVGIS). 18.7% below the median of the main cities of Spain (1,615). #133 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 17.9% more here.

Lugo is in the province of Lugo, Galicia. Population 98,025 (GeoNames). 465 m above sea level. 79 km away: Ourense, the nearest bigger city, 1,354 kWh/kWp — 3.0% less here. 7.38 m between rows, pitch 11.30 m, GCR 0.42 (latitude 43.0°).

Yield of 1 kWp
1,314kWh/year
Tilt
35°10° west of south
10 kW
13,135kWh/year
Row pitch
11.30m · GCR 0.42
Rank in the country
133of 147 cities

Ground frame designer

A ground frame for a solar plant: Lugo

Latitude 43.0°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

66Jan85Feb113Mar122Apr137May134Jun153Jul149Aug126Sep100Oct66Nov61Dec

July: 153 kWh/kWp, December: 61 — 2.5 times less.

December: 61 against the median of 103 for the main cities of Spain, 40.8% less.

Lugo: plants, kWh
kWpA yearJulyDecember
56,568765305
1013,1351,530610
1519,7032,295915

Fixed tilt facing south

What a table yields at another tilt than the optimal 35° — for roofs and frames with a standard slope.

Lugo: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
35° (optimum)1,314—
15°1,248−5.0%
30°1,304−0.7%
45°1,294−1.5%
90°869−33.8%

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.