Solar plant: site data

Solar power plant in Serdyte, Horlivskyi Raion, Donetsk Oblast

Serdyte: 1,154 kWh per kWp a year, tilt 36° facing south (PVGIS). 0.6% below the oblast median (1,161). #60 of 130 in the rayon, #982 of 1312 in the oblast.

Horlivka, the rayon centre, is 40 km away. 257 m above sea level. 35 km away: Makiyivka, the nearest bigger centre, 1,167 — 1.1% less here. Snow and wind from the nearest regional centre in the DBN — Запоріжжя, 243 km. 10.24 m between rows, pitch 14.11 m (latitude 48.0°).

Yield of 1 kWp
1,154kWh/year
Tilt
36°facing south
10 kW
11,543kWh/year
Row pitch
14.11m · GCR 0.34
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
1,110 / 460Pa

Ground frame designer

A ground frame for a solar plant: Serdyte

The designer opens with this place’s coordinates, latitude 48.0° for the row spacing and the DBN loads of the nearest regional centre — Запоріжжя, 243 km: snow 1,110 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

38Jan54Feb87Mar115Apr136May141Jun146Jul148Aug124Sep89Oct47Nov28Dec

August: 148 kWh/kWp, December: 28 — 5.3 times less.

March: 87 against 92 in the oblast, 5.4% less.

Serdyte: plants, kWh
kWpA yearAugustDecember
55,772740140
1011,5431,480280
1517,3152,220420

Snow and wind: Запоріжжя

Example: a 10 kW ground frame

For the loads of Zaporizhzhia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Horlivskyi RaionDonetsk Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.