Solar plant: site data

Solar power plant in Nevelske, Pokrovskyi Raion, Donetsk Oblast

Nevelske: 1,168 kWh per kWp a year, tilt 36° 1° east of south (PVGIS). 0.6% above the oblast median (1,161). #34 of 262 in the rayon, #475 of 1312 in the oblast.

Pokrovsk, the rayon centre, is 38 km away. 192 m above sea level. 17 km away: Donetsk, the nearest bigger centre, the same 1,170. Snow and wind from the nearest regional centre in the DBN — Запоріжжя, 183 km. 10.25 m between rows, pitch 14.12 m (latitude 48.1°).

Yield of 1 kWp
1,168kWh/year
Tilt
36°1° east of south
10 kW
11,680kWh/year
Row pitch
14.12m · GCR 0.34
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
1,110 / 460Pa

Ground frame designer

A ground frame for a solar plant: Nevelske

The designer opens with this place’s coordinates, latitude 48.1° for the row spacing and the DBN loads of the nearest regional centre — Запоріжжя, 183 km: snow 1,110 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

40Jan58Feb92Mar114Apr136May141Jun147Jul149Aug123Sep91Oct48Nov29Dec

August: 149 kWh/kWp, December: 29 — 5.1 times less.

January: 40 against 37 in the oblast, 8.1% more.

Nevelske: plants, kWh
kWpA yearAugustDecember
55,840745145
1011,6801,490290
1517,5202,235435

Snow and wind: Запоріжжя

Example: a 10 kW ground frame

For the loads of Zaporizhzhia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Pokrovskyi RaionDonetsk Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.