Solar plant: site data

Solar power plant in Derylove, Kramatorskyi Raion, Donetsk Oblast

Derylove: 1,146 kWh per kWp a year, tilt 37° facing south (PVGIS). 1.3% below the oblast median (1,161). #203 of 233 in the rayon, #1247 of 1312 in the oblast.

Kramatorsk, the rayon centre, is 39 km away. 123 m above sea level. 36 km away: Izyum, the nearest bigger centre, the same 1,147. Snow and wind from the nearest regional centre in the DBN — Харків, 150 km. 11.27 m between rows, pitch 15.09 m (latitude 49.1°).

Yield of 1 kWp
1,146kWh/year
Tilt
37°facing south
10 kW
11,464kWh/year
Row pitch
15.09m · GCR 0.32
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
1,600 / 430Pa

Ground frame designer

A ground frame for a solar plant: Derylove

The designer opens with this place’s coordinates, latitude 49.1° for the row spacing and the DBN loads of the nearest regional centre — Харків, 150 km: snow 1,600 Pa, wind 430 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

40Jan61Feb93Mar114Apr134May141Jun145Jul147Aug121Sep84Oct42Nov24Dec

August: 147 kWh/kWp, December: 24 — 6.1 times less.

December: 24 against 28 in the oblast, 14.3% less.

Derylove: plants, kWh
kWpA yearAugustDecember
55,732735120
1011,4641,470240
1517,1962,205360

Snow and wind: Харків

Example: a 10 kW ground frame

For the loads of Kharkiv: 11.16 kWp, 18 panels, 385 kg of steel, 12 piles, materials ≈ 51,876 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Kramatorskyi RaionDonetsk Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.