Solar plant: site data

Solar power plant in Velyke, Vyzhnytskyi Raion, Chernivtsi Oblast

Velyke: 1,122 kWh per kWp a year, tilt 38° 1° east of south (PVGIS). 1.8% below the oblast median (1,143). #28 of 94 in the rayon, #339 of 422 in the oblast.

Vyzhnytsya, the rayon centre, is 20 km away. 544 m above sea level — above 500 m the DBN snow and wind are higher. 20 km away: Vyzhnytsya, the nearest bigger centre, 1,076 — 4.2% more here. Snow and wind from the nearest regional centre in the DBN — Чернівці, 42 km. 10.81 m between rows, pitch 14.58 m (latitude 48.2°).

Yield of 1 kWp
1,122kWh/year
Tilt
38°1° east of south
10 kW
11,219kWh/year
Row pitch
14.58m · GCR 0.33
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,320 / 500Pa

Ground frame designer

A ground frame for a solar plant: Velyke

The designer opens with this place’s coordinates, latitude 48.2° for the row spacing and the DBN loads of the nearest regional centre — Чернівці, 42 km: snow 1,320 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

53Jan66Feb97Mar110Apr121May119Jun131Jul129Aug109Sep89Oct54Nov44Dec

July: 131 kWh/kWp, December: 44 — 3.0 times less.

December: 44 against 37 in the oblast, 18.9% more.

Velyke: plants, kWh
kWpA yearJulyDecember
55,610655220
1011,2191,310440
1516,8291,965660

Snow and wind: Чернівці

Example: a 10 kW ground frame

For the loads of Chernivtsi: 11.16 kWp, 18 panels, 412 kg of steel, 16 piles, materials ≈ 54,638 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Vyzhnytskyi RaionChernivtsi Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.