Solar plant: site data

Solar power plant in Tuzhar, Chernihivskyi Raion, Chernihiv Oblast

Tuzhar: 1,112 kWh per kWp a year, tilt 38° 2° east of south (PVGIS). Exactly the oblast median (1,108). #154 of 479 in the rayon, #600 of 1558 in the oblast.

Chernihiv, the rayon centre, is 58 km away. 109 m above sea level. 58 km away: Chernihiv, the nearest bigger centre, 1,105 — 0.6% more here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 58 km. 13.59 m between rows, pitch 17.36 m (latitude 51.2°).

Yield of 1 kWp
1,112kWh/year
Tilt
38°2° east of south
10 kW
11,120kWh/year
Row pitch
17.36m · GCR 0.28
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,720 / 410Pa

Ground frame designer

A ground frame for a solar plant: Tuzhar

The designer opens with this place’s coordinates, latitude 51.2° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 58 km: snow 1,720 Pa, wind 410 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

35Jan54Feb95Mar118Apr138May143Jun142Jul138Aug112Sep77Oct33Nov26Dec

June: 143 kWh/kWp, December: 26 — 5.5 times less.

December: 26 against 24 in the oblast, 8.3% more.

Tuzhar: plants, kWh
kWpA yearJuneDecember
55,560715130
1011,1201,430260
1516,6802,145390

Snow and wind: Чернігів

Example: a 10 kW ground frame

For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Chernihivskyi RaionChernihiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.