Solar plant: site data

Solar power plant in Vasyleva Huta, Chernihivskyi Raion, Chernihiv Oblast

Vasyleva Huta: 1,089 kWh per kWp a year, tilt 38° 3° east of south (PVGIS). 1.7% below the oblast median (1,108). #385 of 479 in the rayon, #1223 of 1558 in the oblast.

Chernihiv, the rayon centre, is 47 km away. 115 m above sea level. 47 km away: Chernihiv, the nearest bigger centre, 1,105 — 1.5% less here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 46 km. 13.72 m between rows, pitch 17.49 m (latitude 51.3°).

Yield of 1 kWp
1,089kWh/year
Tilt
38°3° east of south
10 kW
10,888kWh/year
Row pitch
17.49m · GCR 0.27
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,720 / 410Pa

Ground frame designer

A ground frame for a solar plant: Vasyleva Huta

The designer opens with this place’s coordinates, latitude 51.3° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 46 km: snow 1,720 Pa, wind 410 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan56Feb94Mar115Apr134May138Jun137Jul134Aug110Sep76Oct33Nov26Dec

June: 138 kWh/kWp, December: 26 — 5.3 times less.

December: 26 against 24 in the oblast, 8.3% more.

Vasyleva Huta: plants, kWh
kWpA yearJuneDecember
55,444690130
1010,8881,380260
1516,3322,070390

Snow and wind: Чернігів

Example: a 10 kW ground frame

For the loads of Chernihiv: 11.16 kWp, 18 panels, 363 kg of steel, 12 piles, materials ≈ 54,473 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Chernihivskyi RaionChernihiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.