Solar plant: site data
Solar power plant in Tupychiv, Chernihivskyi Raion, Chernihiv Oblast
Tupychiv: 1,095 kWh per kWp a year, tilt 38° 1° east of south (PVGIS). 1.2% below the oblast median (1,108). #339 of 479 in the rayon, #1101 of 1558 in the oblast.
Chernihiv, the rayon centre, is 31 km away. 137 m above sea level. 31 km away: Chernihiv, the nearest bigger centre, 1,105 — 1.0% less here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 33 km. 14.31 m between rows, pitch 18.08 m (latitude 51.8°).
- Yield of 1 kWp
- 1,095kWh/year
- Tilt
- 38°1° east of south
- 10 kW
- 10,947kWh/year
- Row pitch
- 18.08m · GCR 0.26
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,720 / 410Pa
Ground frame designer
A ground frame for a solar plant: Tupychiv
The designer opens with this place’s coordinates, latitude 51.8° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 33 km: snow 1,720 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
June: 143 kWh/kWp, December: 22 — 6.5 times less.
January: 31 against 35 in the oblast, 11.4% less.
| kWp | A year | June | December |
|---|---|---|---|
| 5 | 5,474 | 715 | 110 |
| 10 | 10,947 | 1,430 | 220 |
| 15 | 16,421 | 2,145 | 330 |
Example: a 10 kW ground frame
For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.
How these numbers are computed
Nearby
- Topolivka2 km1,107 kWh/kWp
- Velykyi Lystven4 km1,096 kWh/kWp
- Vykhvostiv5 km1,108 kWh/kWp
- Kulykivka5 km1,104 kWh/kWp
- Burivka7 km1,104 kWh/kWp
- Ivashkivka8 km1,106 kWh/kWp
All places: Chernihivskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.