Solar plant: site data
Solar power plant in Shaboltasivka, Novhorod-Siverskyi Raion, Chernihiv Oblast
Shaboltasivka: 1,094 kWh per kWp a year, tilt 39° 2° east of south (PVGIS). 1.2% below the oblast median (1,108). #65 of 247 in the rayon, #1112 of 1558 in the oblast.
Novhorod-Siverskyi, the rayon centre, is 39 km away. 178 m above sea level. 39 km away: Novhorod-Siverskyi, the nearest bigger centre, 1,083 — 1.0% more here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 111 km. 14.63 m between rows, pitch 18.35 m (latitude 51.8°).
- Yield of 1 kWp
- 1,094kWh/year
- Tilt
- 39°2° east of south
- 10 kW
- 10,941kWh/year
- Row pitch
- 18.35m · GCR 0.26
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,720 / 410Pa
Ground frame designer
A ground frame for a solar plant: Shaboltasivka
The designer opens with this place’s coordinates, latitude 51.8° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 111 km: snow 1,720 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
June: 140 kWh/kWp, December: 24 — 5.8 times less.
January: 38 against 35 in the oblast, 8.6% more.
| kWp | A year | June | December |
|---|---|---|---|
| 5 | 5,471 | 700 | 120 |
| 10 | 10,941 | 1,400 | 240 |
| 15 | 16,412 | 2,100 | 360 |
Example: a 10 kW ground frame
For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.
How these numbers are computed
Nearby
- Avdiyivka3 km1,091 kWh/kWp
- Ponornytsia6 km1,093 kWh/kWp
- Pokoshychi8 km1,094 kWh/kWp
- Verba9 km1,091 kWh/kWp
- Loska9 km1,079 kWh/kWp
- Verba9 km1,088 kWh/kWp
All places: Novhorod-Siverskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.