Solar power plant in Nova Hreblia, Prylutskyi Raion, Chernihiv Oblast

Nova Hreblia: 1,128 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 1.8% above the oblast median (1,108). #11 of 285 in the rayon, #54 of 1558 in the oblast.

Pryluky, the rayon centre, is 21 km away. 104 m above sea level. 21 km away: Pryluky, the nearest bigger centre, 1,116 — 1.0% more here. Snow and wind from the nearest regional centre in the DBN — Черкаси, 112 km. 12.48 m between rows, pitch 16.30 m (latitude 50.4°).

Yield of 1 kWp
1,128kWh/year
Tilt
37°2° east of south
10 kW
11,276kWh/year
Row pitch
16.30m · GCR 0.29
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Nova Hreblia

The designer opens with this place’s coordinates, latitude 50.4° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 112 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan58Feb95Mar118Apr140May142Jun145Jul142Aug113Sep79Oct36Nov25Dec

July: 145 kWh/kWp, December: 25 — 5.8 times less.

November: 36 against 33 in the oblast, 9.1% more.

Nova Hreblia: plants, kWh
kWpA yearJulyDecember
55,638725125
1011,2761,450250
1516,9142,175375

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed