Solar plant: site data
Solar power plant in Mistky, Koriukivskyi Raion, Chernihiv Oblast
Mistky: 1,072 kWh per kWp a year, tilt 39° 3° east of south (PVGIS). 3.3% below the oblast median (1,108). #215 of 220 in the rayon, #1516 of 1558 in the oblast.
Koryukivka, the rayon centre, is 30 km away. 124 m above sea level. 30 km away: Koryukivka, the nearest bigger centre, 1,085 — 1.2% less here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 78 km. 14.94 m between rows, pitch 18.66 m (latitude 52.0°).
- Yield of 1 kWp
- 1,072kWh/year
- Tilt
- 39°3° east of south
- 10 kW
- 10,718kWh/year
- Row pitch
- 18.66m · GCR 0.26
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,720 / 410Pa
Ground frame designer
A ground frame for a solar plant: Mistky
The designer opens with this place’s coordinates, latitude 52.0° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 78 km: snow 1,720 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
June: 138 kWh/kWp, December: 25 — 5.5 times less.
November: 29 against 33 in the oblast, 12.1% less.
| kWp | A year | June | December |
|---|---|---|---|
| 5 | 5,359 | 690 | 125 |
| 10 | 10,718 | 1,380 | 250 |
| 15 | 16,077 | 2,070 | 375 |
Example: a 10 kW ground frame
For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.
How these numbers are computed
Nearby
- Mlynok4 km1,064 kWh/kWp
- Yeline5 km1,075 kWh/kWp
- Luka7 km1,063 kWh/kWp
- Salne8 km1,073 kWh/kWp
- Myshyne9 km1,083 kWh/kWp
- Huta-Studenetska9 km1,073 kWh/kWp
All places: Koriukivskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.