Loshakova Huta: 1,113 kWh per kWp a year, tilt 38° 2° east of south (PVGIS). Exactly the oblast median (1,108). #139 of 479 in the rayon, #563 of 1558 in the oblast.

Chernihiv, the rayon centre, is 69 km away. 108 m above sea level. 51 km away: Vyshhorod, the nearest bigger centre, the same 1,112. Snow and wind from the nearest regional centre in the DBN — Київ, 65 km. 13.43 m between rows, pitch 17.20 m (latitude 51.0°).

Yield of 1 kWp
1,113kWh/year
Tilt
38°2° east of south
10 kW
11,129kWh/year
Row pitch
17.20m · GCR 0.28
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,550 / 370Pa

Ground frame designer

A ground frame for a solar plant: Loshakova Huta

The designer opens with this place’s coordinates, latitude 51.0° for the row spacing and the DBN loads of the nearest regional centre — Київ, 65 km: snow 1,550 Pa, wind 370 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan56Feb96Mar118Apr137May142Jun141Jul137Aug112Sep78Oct34Nov25Dec

June: 142 kWh/kWp, December: 25 — 5.7 times less.

January: 37 against 35 in the oblast, 5.7% more.

Loshakova Huta: plants, kWh
kWpA yearJuneDecember
55,565710125
1011,1291,420250
1516,6942,130375

Snow and wind: Київ

Example: a 10 kW ground frame

For the loads of Kyiv: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 47,122 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed