Solar plant: site data

Solar power plant in Lomanka, Novhorod-Siverskyi Raion, Chernihiv Oblast

Lomanka: 1,096 kWh per kWp a year, tilt 39° 2° east of south (PVGIS). 1.1% below the oblast median (1,108). #59 of 247 in the rayon, #1084 of 1558 in the oblast.

Novhorod-Siverskyi, the rayon centre, is 30 km away. 188 m above sea level. 30 km away: Novhorod-Siverskyi, the nearest bigger centre, 1,083 — 1.2% more here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 119 km. 14.91 m between rows, pitch 18.63 m (latitude 52.0°).

Yield of 1 kWp
1,096kWh/year
Tilt
39°2° east of south
10 kW
10,958kWh/year
Row pitch
18.63m · GCR 0.26
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,720 / 410Pa

Ground frame designer

A ground frame for a solar plant: Lomanka

The designer opens with this place’s coordinates, latitude 52.0° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 119 km: snow 1,720 Pa, wind 410 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan60Feb99Mar115Apr138May141Jun138Jul135Aug107Sep72Oct30Nov24Dec

June: 141 kWh/kWp, December: 24 — 5.9 times less.

November: 30 against 33 in the oblast, 9.1% less.

Lomanka: plants, kWh
kWpA yearJuneDecember
55,479705120
1010,9581,410240
1516,4372,115360

Snow and wind: Чернігів

Example: a 10 kW ground frame

For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Novhorod-Siverskyi RaionChernihiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.