Solar plant: site data

Solar power plant in Ivanivka, Novhorod-Siverskyi Raion, Chernihiv Oblast

Ivanivka: 1,065 kWh per kWp a year, tilt 39° 3° east of south (PVGIS). 3.8% below the oblast median (1,108). #238 of 247 in the rayon, #1532 of 1558 in the oblast.

Novhorod-Siverskyi, the rayon centre, is 42 km away. 141 m above sea level. 42 km away: Novhorod-Siverskyi, the nearest bigger centre, 1,083 — 1.7% less here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 121 km. 15.13 m between rows, pitch 18.85 m (latitude 52.1°).

Yield of 1 kWp
1,065kWh/year
Tilt
39°3° east of south
10 kW
10,653kWh/year
Row pitch
18.85m · GCR 0.25
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,720 / 410Pa

Ground frame designer

A ground frame for a solar plant: Ivanivka

The designer opens with this place’s coordinates, latitude 52.1° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 121 km: snow 1,720 Pa, wind 410 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

35Jan56Feb96Mar113Apr136May138Jun135Jul132Aug104Sep69Oct30Nov23Dec

June: 138 kWh/kWp, December: 23 — 6.0 times less.

November: 30 against 33 in the oblast, 9.1% less.

Ivanivka: plants, kWh
kWpA yearJuneDecember
55,327690115
1010,6531,380230
1515,9802,070345

Snow and wind: Чернігів

Example: a 10 kW ground frame

For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Novhorod-Siverskyi RaionChernihiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.