Solar plant: site data
Solar power plant in Budyshche, Novhorod-Siverskyi Raion, Chernihiv Oblast
Budyshche: 1,095 kWh per kWp a year, tilt 39° 2° east of south (PVGIS). 1.2% below the oblast median (1,108). #64 of 247 in the rayon, #1105 of 1558 in the oblast.
Novhorod-Siverskyi, the rayon centre, is 44 km away. 145 m above sea level. 42 km away: Shostka, the nearest bigger centre, 1,082 — 1.2% more here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 117 km. 14.48 m between rows, pitch 18.20 m (latitude 51.7°).
- Yield of 1 kWp
- 1,095kWh/year
- Tilt
- 39°2° east of south
- 10 kW
- 10,946kWh/year
- Row pitch
- 18.20m · GCR 0.26
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,720 / 410Pa
Ground frame designer
A ground frame for a solar plant: Budyshche
The designer opens with this place’s coordinates, latitude 51.7° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 117 km: snow 1,720 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
June: 141 kWh/kWp, December: 24 — 5.9 times less.
October: 72 against 75 in the oblast, 4.0% less.
| kWp | A year | June | December |
|---|---|---|---|
| 5 | 5,473 | 705 | 120 |
| 10 | 10,946 | 1,410 | 240 |
| 15 | 16,419 | 2,115 | 360 |
Example: a 10 kW ground frame
For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.
How these numbers are computed
Nearby
- Horodyshche4 km1,102 kWh/kWp
- Prydesnianske4 km1,102 kWh/kWp
- Chorniavka4 km1,102 kWh/kWp
- Obolonnia5 km1,099 kWh/kWp
- Chereshenky6 km1,101 kWh/kWp
- Rykhly7 km1,093 kWh/kWp
All places: Novhorod-Siverskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.