Solar plant: site data

Solar power plant in Veselyi Podil, Zolotoniskyi Raion, Cherkasy Oblast

Veselyi Podil: 1,155 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 0.9% above the oblast median (1,144). #47 of 160 in the rayon, #107 of 731 in the oblast.

Zolotonosha, the rayon centre, is 36 km away. 120 m above sea level. 36 km away: Zolotonosha, the nearest bigger centre, the same 1,156. Snow and wind from the nearest regional centre in the DBN — Черкаси, 40 km. 11.75 m between rows, pitch 15.57 m (latitude 49.6°).

Yield of 1 kWp
1,155kWh/year
Tilt
37°2° east of south
10 kW
11,548kWh/year
Row pitch
15.57m · GCR 0.31
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Veselyi Podil

The designer opens with this place’s coordinates, latitude 49.6° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 40 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

35Jan56Feb95Mar121Apr142May145Jun148Jul145Aug117Sep86Oct39Nov26Dec

July: 148 kWh/kWp, December: 26 — 5.7 times less.

December: 26 against 28 in the oblast, 7.1% less.

Veselyi Podil: plants, kWh
kWpA yearJulyDecember
55,774740130
1011,5481,480260
1517,3222,220390

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zolotoniskyi RaionCherkasy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.