Solar power plant in Senkivtsi, Zolotoniskyi Raion, Cherkasy Oblast

Senkivtsi: 1,145 kWh per kWp a year, tilt 37° 1° east of south (PVGIS). Exactly the oblast median (1,144). #89 of 160 in the rayon, #319 of 731 in the oblast.

Zolotonosha, the rayon centre, is 11 km away. 116 m above sea level. 11 km away: Zolotonosha, the nearest bigger centre, 1,156 — 0.9% less here. Snow and wind from the nearest regional centre in the DBN — Черкаси, 36 km. 11.87 m between rows, pitch 15.69 m (latitude 49.8°).

Yield of 1 kWp
1,145kWh/year
Tilt
37°1° east of south
10 kW
11,453kWh/year
Row pitch
15.69m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Senkivtsi

The designer opens with this place’s coordinates, latitude 49.8° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 36 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan58Feb97Mar119Apr139May142Jun147Jul144Aug115Sep85Oct37Nov26Dec

July: 147 kWh/kWp, December: 26 — 5.7 times less.

December: 26 against 28 in the oblast, 7.1% less.

Senkivtsi: plants, kWh
kWpA yearJulyDecember
55,727735130
1011,4531,470260
1517,1802,205390

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zolotoniskyi RaionCherkasy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.