Section of the table from the Solispec engine (median zone — Cherkasy)

GCL

Ground frame for 30 GCL-NT10/78GDF 640 panels (2×15)

2 rows of 15 panels, 19.20 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
19.20kW
Steel
564.4kg
Posts
20
Bolts
206
Materials
79,187₴
Yield
21,865kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the GCL-NT10/78GDF 640 panel and the 2 × 15 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 60×40×2C-channel 80×40×2C-channel 80×40×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames10 frames, pitch up to 1,870 mm10 frames, pitch up to 1,870 mm10 frames, pitch up to 1,870 mm
Posts202020
Footings (bored concrete)20 pcs, Ø400 mm, depth 1,100 mm20 pcs, Ø350 mm, depth 1,100 mm20 pcs, Ø300 mm, depth 1,300 mm
Concrete3.04 m³2.33 m³2.02 m³
Tilt30°30°30°
Panel bottom / post top600 / 2,347 mm600 / 2,338 mm600 / 2,338 mm
Panel field size17,430 × 3,206 mm17,430 × 3,211 mm17,430 × 3,211 mm
Row spacing between tables (no shade on 21 December)11,110 mm at noon · 12,490 mm ±2 h12,310 mm at noon · 14,210 mm ±2 h13,490 mm at noon · 16,030 mm ±2 h
Steel569.3 kg564.4 kg578.8 kg
BoltsM10 — 142, M8 — 64M10 — 142, M8 — 64M10 — 142, M8 — 64
Panel clampsend 8, middle 56end 8, middle 56end 8, middle 56
Materials74,619 UAH79,187 UAH84,712 UAH
With installation and delivery123,504 UAH128,072 UAH133,597 UAH
Per 1 kW6,433 UAH/kW6,670 UAH/kW6,958 UAH/kW
Yield1,266 kWh/kW · 24,315 kWh/year1,139 kWh/kW · 21,865 kWh/year1,043 kWh/kW · 20,028 kWh/year
Strength σ/fy60%82%88%
Deflection / (L/200)44%60%64%
Rafter strength94%87%93%
Post utilisation18%25%27%
Utilisation97%100%99%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Kherson: Rafter C-channel 60×40×2: span between posts 2 349, cantilever 851 mm → strength 94%.Cherkasy: Rafter C-channel 80×40×2: span between posts 2 349, cantilever 851 mm → strength 87%.Chernihiv: Rafter C-channel 80×40×2: span between posts 2 349, cantilever 851 mm → strength 93%.
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø400 × 1 100: 0.138 m³ of concrete per post. Wind uplift on the front post ≈ 12.9 kN (with γ=1.5) vs ≈ 13.4 kN (concrete weight + soil friction, estimate) → 97%.Cherkasy: Foundation Ø350 × 1 100: 0.106 m³ of concrete per post. Wind uplift on the front post ≈ 11.3 kN (with γ=1.5) vs ≈ 11.4 kN (concrete weight + soil friction, estimate) → 100%.Chernihiv: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 11.0 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 99%.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Cherkasy: Frame spacing 1 870 mm, 10 frames. Purlin C-channel 60×40×2: strength 82%, deflection 60% of L/200 (snow on panel 977 Pa).Chernihiv: Frame spacing 1 870 mm, 10 frames. Purlin C-channel 60×40×2: strength 88%, deflection 64% of L/200 (snow on panel 1 106 Pa).

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,28910
П2Rear postTube 60×60×23,46310
Кр1Rafter (inclined beam)C-channel 80×40×24,05010
Пк1Frame strutC-channel 60×40×21,86310
Х1Longitudinal brace (cross)C-channel 60×40×22,5364
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×26,0002
Р4Purlin (rail)C-channel 60×40×26,0002
Р5Purlin (rail)C-channel 60×40×25,4302
Р6Purlin (rail)C-channel 60×40×25,4302
—Bolt M10×25 set · purlins, braces, connectors——34
—Bolt M10×90 set · strut to post — through spacer inserts——10
—Bolt M10×100 set · purlin to rafter——40
—Bolt M10×130 set · post–rafter — through spacer inserts——40
—Bolt M10×140 set · strut to rafter — through spacer inserts——10
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 30 mm——8
—Mid clamp (30–40 mm)——56
—Bolt M8×50 + channel nut——64
—Concrete for 20 posts, Ø350×1100——2.33 m³

Profile cutting

38 bars of 6,000 mm, 196.5 m of profile in total.

  • Tube 60×60×210 bars
  • C-channel 80×40×210 bars
  • C-channel 60×40×218 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
79,187₴
With installation and delivery
128,072₴
Per 1 kW
6,670UAH/kW

The engine's estimate has 24 lines; the full list is in the builder. Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 21,865 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.