Section of the table from the Solispec engine (median zone — Cherkasy)

DMEGC

Ground frame for 10 DMEGC Infinity RT DM450M10RT-B54HBB panels (1×10)

1 row of 10 panels, 4.50 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
4.50kW
Steel
213.0kg
Posts
12
Bolts
88
Materials
30,067₴
Yield
5,125kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the DMEGC Infinity RT DM450M10RT-B54HBB panel and the 1 × 10 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersTube 60×60×2Tube 60×60×2Tube 60×60×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames5 frames, pitch up to 2,710 mm6 frames, pitch up to 2,200 mm6 frames, pitch up to 2,200 mm
Posts101212
Footings (bored concrete)10 pcs, Ø300 mm, depth 900 mm12 pcs, Ø300 mm, depth 1,100 mm12 pcs, Ø300 mm, depth 1,300 mm
Concrete0.70 m³1.03 m³1.21 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,134 mm600 / 1,134 mm600 / 1,134 mm
Panel field size11,660 × 1,105 mm11,660 × 1,105 mm11,660 × 1,105 mm
Row spacing between tables (no shade on 21 December)3,960 mm at noon · 4,450 mm ±2 h4,380 mm at noon · 5,060 mm ±2 h4,810 mm at noon · 5,710 mm ±2 h
Steel189.6 kg213.0 kg221.6 kg
BoltsM10 — 58, M8 — 22M10 — 66, M8 — 22M10 — 66, M8 — 22
Panel clampsend 4, middle 18end 4, middle 18end 4, middle 18
Materials26,579 UAH30,067 UAH32,263 UAH
With installation and delivery39,264 UAH42,747 UAH44,943 UAH
Per 1 kW8,725 UAH/kW9,499 UAH/kW9,987 UAH/kW
Yield1,266 kWh/kW · 5,699 kWh/year1,139 kWh/kW · 5,125 kWh/year1,043 kWh/kW · 4,694 kWh/year
Strength σ/fy84%77%83%
Deflection / (L/200)90%67%72%
Rafter strength7%8%9%
Post utilisation5%6%6%
Utilisation74%43%36%
Depth vs frost depthokokok
Checks overallwith a cautionpasseswith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Kherson: Frame spacing 2 710 mm, 5 frames. Purlin C-channel 60×40×2: strength 84%, deflection 90% of L/200 (snow on panel 489 Pa).Chernihiv: Frame spacing 2 200 mm, 6 frames. Purlin C-channel 60×40×2: strength 83%, deflection 72% of L/200 (snow on panel 1 106 Pa).

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×21,9166
П2Rear postTube 60×60×22,2596
Кр1Rafter (inclined beam)Tube 60×60×21,1826
Пк1Frame strutC-channel 60×40×28226
Х1Longitudinal brace (cross)C-channel 60×40×22,2924
Р1Purlin (rail)C-channel 60×40×26,0001
Р2Purlin (rail)C-channel 60×40×26,0001
Р3Purlin (rail)C-channel 60×40×25,6601
Р4Purlin (rail)C-channel 60×40×25,6601
—Bolt M10×140 / M10×80 set · frame and struts / purlins, braces, connectors——52
—Bolt M10×150 set · brace to post, strut to rafter — through spacer inserts——14
—End clamp 30 mm——4
—Mid clamp (30–40 mm)——18
—Bolt M8×50 + channel nut——22
—Concrete for 12 posts, Ø300×1100——1.03 m³

Profile cutting

13 bars of 6,000 mm, 69.6 m of profile in total.

  • Tube 60×60×26 bars
  • C-channel 60×40×27 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
30,067₴
With installation and delivery
42,747₴
Per 1 kW
9,499UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 20 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 60×60×2, stock length 6 000 mm6 bar2107,560
C-channel 60×40×2, stock length 6 000 mm7 bar2309,660
C-channel connector (splice plate L 300)2 pcs90180
Bolt M10×140 cl. 8.8 set — frame, struts37 pcs22814
Bolt M10×80 cl. 8.8 set — purlins, braces, connectors22 pcs22484
Bolt M10×150 cl. 8.8 set — strut to rafter, brace to post — through spacer inserts14 pcs27378
End clamp 30 mm4 pcs35140
Mid clamp (30–40 mm)18 pcs32576
Bolt M8×50 A2 + spring channel nut M825 pcs14350
Post base anchor pin (M10 / rebar Ø12)12 pcs20240
Borehole casing (roofing felt / PVC, 300 mm)12 pcs60720
Crushed stone 20–40 for the bottom of the boreholes0.08 m³90072
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow29 m351,015
Module earthing clip (under the clamp)10 pcs20200
Cable clip, stainless30 pcs5150
Zinc paint / cold galvanising spray 400 ml1 pcs350350
Concrete M200 for posts1.03 m³3,8003,914
Rebar Ø10 (4 bars per post)63 m281,764
Spacer inserts / packs — pieces of the same profile (from offcuts): 4 × 71 mm, 6 × 70 mm, 4 × 30 mm, 6 × 10 mm20 pcs00
Materials30,067

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 5,125 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.

Other layouts of this panel

The 1×10 layout with other panels

Next