Section of the table from the Solispec engine (median zone — Cherkasy)

DAS Solar

Ground frame for 16 DAS Solar D-Mini DAS-DH108NA-440 panels (2×8)

2 rows of 8 panels, 7.04 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
7.04kW
Steel
269.6kg
Posts
10
Bolts
112
Materials
36,356₴
Yield
8,017kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the DAS Solar D-Mini DAS-DH108NA-440 panel and the 2 × 8 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames5 frames, pitch up to 2,170 mm5 frames, pitch up to 2,170 mm5 frames, pitch up to 2,170 mm
Posts101010
Footings (bored concrete)10 pcs, Ø350 mm, depth 1,100 mm10 pcs, Ø300 mm, depth 1,100 mm10 pcs, Ø300 mm, depth 1,300 mm
Concrete1.16 m³0.86 m³1.01 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,809 mm600 / 1,809 mm600 / 1,809 mm
Panel field size9,352 × 2,274 mm9,352 × 2,274 mm9,352 × 2,274 mm
Row spacing between tables (no shade on 21 December)7,770 mm at noon · 8,740 mm ±2 h8,610 mm at noon · 9,950 mm ±2 h9,440 mm at noon · 11,220 mm ±2 h
Steel269.6 kg269.6 kg276.8 kg
BoltsM10 — 76, M8 — 36M10 — 76, M8 — 36M10 — 76, M8 — 36
Panel clampsend 8, middle 28end 8, middle 28end 8, middle 28
Materials37,523 UAH36,356 UAH37,150 UAH
With installation and delivery56,293 UAH55,126 UAH55,920 UAH
Per 1 kW7,996 UAH/kW7,830 UAH/kW7,943 UAH/kW
Yield1,266 kWh/kW · 8,916 kWh/year1,139 kWh/kW · 8,017 kWh/year1,043 kWh/kW · 7,344 kWh/year
Strength σ/fy54%75%80%
Deflection / (L/200)46%64%68%
Rafter strength54%74%80%
Post utilisation11%15%16%
Utilisation84%88%73%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø350 × 1 100: 0.106 m³ of concrete per post. Wind uplift on the front post ≈ 9.6 kN (with γ=1.5) vs ≈ 11.4 kN (concrete weight + soil friction, estimate) → 84%.Cherkasy: Foundation Ø300 × 1 100: 0.078 m³ of concrete per post. Wind uplift on the front post ≈ 8.4 kN (with γ=1.5) vs ≈ 9.5 kN (concrete weight + soil friction, estimate) → 88%.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Chernihiv: Frame spacing 2 170 mm, 5 frames. Purlin C-channel 60×40×2: strength 80%, deflection 68% of L/200 (snow on panel 1 106 Pa).

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,0925
П2Rear postTube 60×60×22,9345
Кр1Rafter (inclined beam)C-channel 60×40×22,9045
Пк1Frame strutC-channel 60×40×21,4025
Х1Longitudinal brace (cross)C-channel 60×40×22,4874
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×23,3522
Р4Purlin (rail)C-channel 60×40×23,3522
—Bolt M10×25 set · purlins, braces, connectors——18
—Bolt M10×80 set · purlin to rafter——20
—Bolt M10×90 set · strut to post — through spacer inserts——5
—Bolt M10×130 set · post–rafter — through spacer inserts——20
—Bolt M10×140 set · strut to rafter — through spacer inserts——5
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 30 mm——8
—Mid clamp (30–40 mm)——28
—Bolt M8×50 + channel nut——36
—Concrete for 10 posts, Ø300×1100——0.86 m³

Profile cutting

17 bars of 6,000 mm, 94.0 m of profile in total.

  • Tube 60×60×25 bars
  • C-channel 60×40×212 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
36,356₴
With installation and delivery
55,126₴
Per 1 kW
7,830UAH/kW

The engine's estimate has 23 lines; the full list is in the builder. Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 8,017 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.