Section of the table from the Solispec engine (median zone — Cherkasy)

Canadian Solar

Ground frame for 60 Canadian Solar TOPHiKu6 CS6.2-54TD-530 panels (3×20)

3 rows of 20 panels, 31.80 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
31.80kW
Steel
1,141.9kg
Posts
26
Bolts
390
Materials
155,132₴
Yield
36,213kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Canadian Solar TOPHiKu6 CS6.2-54TD-530 panel and the 3 × 20 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 80×40×2C-channel 100×50×2.5C-channel 100×50×2.5
Purlins and bracesC-channel 41×41×2.5C-channel 60×40×2C-channel 60×40×2
Frames17 frames, pitch up to 1,420 mm13 frames, pitch up to 1,890 mm13 frames, pitch up to 1,890 mm
Posts342626
Footings (bored concrete)34 pcs, Ø400 mm, depth 1,100 mm26 pcs, Ø400 mm, depth 1,300 mm26 pcs, Ø350 mm, depth 1,500 mm
Concrete5.17 m³4.67 m³4.13 m³
Tilt30°30°30°
Panel bottom / post top600 / 2,771 mm600 / 2,746 mm600 / 2,746 mm
Panel field size23,200 × 3,922 mm23,200 × 3,936 mm23,200 × 3,936 mm
Row spacing between tables (no shade on 21 December)13,290 mm at noon · 14,940 mm ±2 h14,730 mm at noon · 17,010 mm ±2 h16,140 mm at noon · 19,180 mm ±2 h
Steel1,225.5 kg1,141.9 kg1,160.6 kg
BoltsM10 — 320, M8 — 126M10 — 264, M8 — 126M10 — 264, M8 — 126
Panel clampsend 12, middle 114end 12, middle 114end 12, middle 114
Materials162,837 UAH155,132 UAH153,596 UAH
With installation and delivery242,544 UAH235,112 UAH233,576 UAH
Per 1 kW7,627 UAH/kW7,393 UAH/kW7,345 UAH/kW
Yield1,266 kWh/kW · 40,272 kWh/year1,139 kWh/kW · 36,213 kWh/year1,043 kWh/kW · 33,171 kWh/year
Strength σ/fy51%67%72%
Deflection / (L/200)36%50%54%
Rafter strength83%76%81%
Post utilisation21%37%40%
Utilisation92%91%90%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Kherson: Rafter C-channel 80×40×2: span between posts 3 041, cantilever 1 101 mm → strength 83%.Chernihiv: Rafter C-channel 100×50×2.5: span between posts 3 041, cantilever 1 101 mm → strength 81%.
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø400 × 1 100: 0.138 m³ of concrete per post. Wind uplift on the front post ≈ 12.3 kN (with γ=1.5) vs ≈ 13.4 kN (concrete weight + soil friction, estimate) → 92%.Cherkasy: Foundation Ø400 × 1 300: 0.163 m³ of concrete per post. Wind uplift on the front post ≈ 14.3 kN (with γ=1.5) vs ≈ 15.8 kN (concrete weight + soil friction, estimate) → 91%.Chernihiv: Foundation Ø350 × 1 500: 0.144 m³ of concrete per post. Wind uplift on the front post ≈ 14.0 kN (with γ=1.5) vs ≈ 15.5 kN (concrete weight + soil friction, estimate) → 90%.

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,55013
П2Rear postTube 60×60×24,07113
Кр1Rafter (inclined beam)C-channel 100×50×2.55,24313
Пк1Frame strutC-channel 60×40×22,22813
Пк2Front frame strutC-channel 60×40×22,94413
Х1Longitudinal brace (cross)C-channel 60×40×22,8354
Р1Purlin (rail)C-channel 60×40×26,0003
Р2Purlin (rail)C-channel 60×40×26,0003
Р3Purlin (rail)C-channel 60×40×26,0003
Р4Purlin (rail)C-channel 60×40×26,0003
Р5Purlin (rail)C-channel 60×40×26,0003
Р6Purlin (rail)C-channel 60×40×26,0003
Р7Purlin (rail)C-channel 60×40×25,2003
Р8Purlin (rail)C-channel 60×40×25,2003
—Bolt M10×80 / M10×25 set · frame and struts / purlins, braces, connectors——87
—Bolt M10×90 set · strut to post — through spacer inserts——13
—Bolt M10×120 set · purlin to rafter——78
—Bolt M10×130 set · post–rafter, strut to post — through spacer inserts——65
—Bolt M10×140 set · strut to rafter — through spacer inserts——13
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 30 mm——12
—Mid clamp (30–40 mm)——114
—Bolt M8×50 + channel nut——126
—Concrete for 26 posts, Ø400×1300——4.67 m³

Profile cutting

72 bars of 6,000 mm, 372.0 m of profile in total.

  • Tube 60×60×220 bars
  • C-channel 100×50×2.513 bars
  • C-channel 60×40×239 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
155,132₴
With installation and delivery
235,112₴
Per 1 kW
7,393UAH/kW

The engine's estimate has 25 lines; the full list is in the builder. Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 36,213 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.