Section of the table from the Solispec engine (median zone — Cherkasy)

Canadian Solar

Ground frame for 30 Canadian Solar TOPHiKu6 CS6.2-48TD-450 (All-Black) panels (2×15)

2 rows of 15 panels, 13.50 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
13.50kW
Steel
481.8kg
Posts
16
Bolts
186
Materials
58,874₴
Yield
15,374kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Canadian Solar TOPHiKu6 CS6.2-48TD-450 (All-Black) panel and the 2 × 15 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersTube 60×60×2Tube 60×60×2Tube 60×60×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames8 frames, pitch up to 2,390 mm8 frames, pitch up to 2,390 mm8 frames, pitch up to 2,390 mm
Posts161616
Footings (bored concrete)16 pcs, Ø400 mm, depth 900 mm16 pcs, Ø300 mm, depth 1,300 mm16 pcs, Ø300 mm, depth 1,300 mm
Concrete1.99 m³1.62 m³1.62 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,838 mm600 / 1,838 mm600 / 1,838 mm
Panel field size17,430 × 2,324 mm17,430 × 2,324 mm17,430 × 2,324 mm
Row spacing between tables (no shade on 21 December)7,950 mm at noon · 8,940 mm ±2 h8,810 mm at noon · 10,180 mm ±2 h9,660 mm at noon · 11,480 mm ±2 h
Steel458.7 kg481.8 kg481.8 kg
BoltsM10 — 122, M8 — 64M10 — 122, M8 — 64M10 — 122, M8 — 64
Panel clampsend 8, middle 56end 8, middle 56end 8, middle 56
Materials58,401 UAH58,874 UAH58,874 UAH
With installation and delivery93,571 UAH94,044 UAH94,044 UAH
Per 1 kW6,931 UAH/kW6,966 UAH/kW6,966 UAH/kW
Yield1,266 kWh/kW · 17,097 kWh/year1,139 kWh/kW · 15,374 kWh/year1,043 kWh/kW · 14,082 kWh/year
Strength σ/fy67%93%100%
Deflection / (L/200)63%87%94%
Rafter strength40%56%60%
Post utilisation13%17%19%
Utilisation99%85%83%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø400 × 900: 0.113 m³ of concrete per post. Wind uplift on the front post ≈ 10.8 kN (with γ=1.5) vs ≈ 10.9 kN (concrete weight + soil friction, estimate) → 99%.Cherkasy: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 9.5 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 85%.Chernihiv: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 9.2 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 83%.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Cherkasy: Frame spacing 2 390 mm, 8 frames. Purlin C-channel 60×40×2: strength 93%, deflection 87% of L/200 (snow on panel 977 Pa).Chernihiv: Frame spacing 2 390 mm, 8 frames. Purlin C-channel 60×40×2: strength 100%, deflection 94% of L/200 (snow on panel 1 106 Pa).

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,3038
П2Rear postTube 60×60×23,1638
Кр1Rafter (inclined beam)Tube 60×60×22,9648
Пк1Frame strutC-channel 60×40×21,4278
Х1Longitudinal brace (cross)C-channel 60×40×22,6974
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×26,0002
Р4Purlin (rail)C-channel 60×40×26,0002
Р5Purlin (rail)C-channel 60×40×25,4302
Р6Purlin (rail)C-channel 60×40×25,4302
—Bolt M10×140 / M10×80 set · frame and struts / purlins, braces, connectors——106
—Bolt M10×150 set · brace to post, strut to rafter — through spacer inserts——16
—End clamp 30 mm——8
—Mid clamp (30–40 mm)——56
—Bolt M8×50 + channel nut——64
—Concrete for 16 posts, Ø300×1300——1.62 m³

Profile cutting

28 bars of 6,000 mm, 159.4 m of profile in total.

  • Tube 60×60×212 bars
  • C-channel 60×40×216 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
58,874₴
With installation and delivery
94,044₴
Per 1 kW
6,966UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 20 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 60×60×2, stock length 6 000 mm12 bar21015,120
C-channel 60×40×2, stock length 6 000 mm16 bar23022,080
C-channel connector (splice plate L 300)8 pcs90720
Bolt M10×140 cl. 8.8 set — frame, struts40 pcs22880
Bolt M10×80 cl. 8.8 set — purlins, braces, connectors79 pcs221,738
Bolt M10×150 cl. 8.8 set — strut to rafter, brace to post — through spacer inserts16 pcs27432
End clamp 30 mm8 pcs35280
Mid clamp (30–40 mm)56 pcs321,792
Bolt M8×50 A2 + spring channel nut M871 pcs14994
Post base anchor pin (M10 / rebar Ø12)16 pcs20320
Borehole casing (roofing felt / PVC, 300 mm)16 pcs60960
Crushed stone 20–40 for the bottom of the boreholes0.11 m³90099
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow39 m351,365
Module earthing clip (under the clamp)30 pcs20600
Cable clip, stainless90 pcs5450
Zinc paint / cold galvanising spray 400 ml2 pcs350700
Concrete M200 for posts1.62 m³3,8006,156
Rebar Ø10 (4 bars per post)96 m282,688
Spacer inserts / packs — pieces of the same profile (from offcuts): 4 × 71 mm, 8 × 70 mm, 4 × 30 mm, 8 × 10 mm24 pcs00
Materials58,874

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 15,374 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.