A grid-tie inverter sends solar power to the house and the grid, but it shuts down when the grid goes. A hybrid does the same and also works with a battery, so it keeps the house running during an outage. An off-grid inverter needs no grid at all: it is the choice for a cabin or a site without a connection. Below is how to match the type to your situation and what to check in the datasheet before you buy.

Three inverter types: what each one does

Grid-tie

A grid-tie inverter turns the panels' direct current into alternating current and synchronises with the grid. The house uses the energy first; the surplus goes to the grid. There is usually no battery in this setup.

The key point: when the grid goes down, a grid-tie inverter shuts off. This is not a defect but mandatory anti-islanding protection. The inverter must not energise a line that electricians may be working on. So even on a sunny day during an outage, the panels on the roof give the house no power at all.

Pros: a simple system, a wide range of sizes (in our inverter catalogue three-phase grid-tie models run from 5 to 110 kW), high efficiency. Con: no backup.

Hybrid

A hybrid inverter combines a grid-tie inverter, a charger and a battery inverter. It can:

  • power the house from the panels and export the surplus;
  • charge the battery from the panels or from the grid;
  • during an outage, disconnect from the grid and power the backup circuits from the panels and the battery.

An important detail: in backup mode it usually powers not the whole house but only the loads wired to the backup output (often labelled EPS, Backup or Load). Which circuits go there is decided at the design stage.

Batteries are either low-voltage (LV, around 48 V) or high-voltage (HV). An inverter supports only one of these classes, so the battery is chosen for a specific model.

Off-grid

An off-grid inverter works without the grid: the panels charge the battery and the inverter powers the loads from it. Without a battery the system does not work. Some models accept a generator or the grid as a backup charging source, but they do not export. In our catalogue the off-grid models are single-phase with low-voltage batteries.

Microinverters and optimisers in brief

A microinverter sits on one or two panels, and each of them works independently. This suits roofs with complex shading or several pitches. An optimiser is a DC device on the panel that works together with an inverter. In both cases the string length and compatibility are checked in the manufacturer's configurator, not with a simple formula.

What happens when the power goes out

  • Grid-tie: with the grid, powers the house and exports the surplus; without it, shuts down completely.
  • Hybrid with battery: with the grid, powers the house, charges the battery and can export; without it, powers the backup circuits from the panels and battery.
  • Hybrid without battery: with the grid, works like a grid-tie inverter; without it, depends on the model — check the datasheet.
  • Off-grid: needs no grid; works as usual while there is charge.

How many hours a battery lasts depends on its capacity, depth of discharge and the load. Work it out in the battery backup calculator: enter what must run during the outage and it shows the hours.

Exporting to the grid and self-consumption

Grid-tie and hybrid inverters can export the surplus. Whether that pays depends on the terms on which you sell energy (a feed-in tariff, net metering or another scheme for households or businesses). In Ukraine these terms have changed more than once, so check the current rules with your grid operator and the regulations in force before you count on export in the payback.

If exporting does not pay or is not allowed, the system is built for self-consumption. Many grid-tie and hybrid inverters can limit export using a meter at the service entrance. A hybrid also stores the daytime surplus in the battery and releases it in the evening. The payback calculator shows how the payback changes in each scenario.

How to choose: a decision tree

  1. No grid on site (cabin, apiary, remote site)? → an off-grid inverter with a battery. Size the capacity for night-time use and cloudy days.
  2. Grid available, but outages are frequent and long? → a hybrid with a battery. Decide the backup circuits in advance: fridge, lighting, router, boiler pump.
  3. Hardly any outages, and the goal is export or lower bills? → a grid-tie inverter. It is simpler and usually cheaper for the same power.
  4. A business or a large house with a three-phase supply? → a three-phase grid-tie or three-phase hybrid. For backup, check how the inverter handles unbalanced load across the phases.
  5. Not sure you will add batteries? → a hybrid without a battery today, a battery later. Make sure the chosen model works this way and note which battery class (LV or HV) it supports.

If you do not know the power you need yet, start with the system size calculator: it estimates it from your consumption.

Single phase or three

A single-phase inverter connects to a single-phase supply. In our catalogue single-phase hybrids range from 3.6 to 11 kW. With a three-phase supply, a single-phase inverter powers only one phase. During an outage the other phases stay dark, and in normal operation feeding one phase creates an imbalance.

A three-phase inverter spreads the power across the phases. It fits a three-phase supply, larger systems and businesses. The final decision depends on your contract with the grid operator and the permitted connection capacity.

DC/AC ratio: how many panels per inverter

The panel power (DC) is often made somewhat larger than the inverter's rated power (AC). Panels rarely deliver their rated output, so moderate oversizing loads the inverter better in the morning and evening.

The guide values Solispec uses in a project:

  • DC/AC up to 1.3 — a normal ratio;
  • above 1.3 — the inverter will clip the peaks in the sunniest hours (clipping);
  • above 1.5 — heavy oversizing, better to take a larger inverter;
  • below 0.7 — the inverter is too big for these panels.

Above all this sits a hard limit: the maximum PV power the manufacturer allows in the datasheet. It must not be exceeded, even if the ratio looks acceptable.

MPPT and the string voltage window

An MPPT is an inverter input that tracks the maximum power point on its own. The more MPPTs, the easier it is to wire panels from different roof pitches or orientations: each pitch on its own input. In the catalogue most single-phase models have 1–3 MPPTs, three-phase ones up to 10.

On each input the string must fit the voltage window:

  • maximum input voltage — never exceeded, even in the hardest frost;
  • MPPT range — the string's operating voltage must stay inside it in both heat and winter;
  • maximum input current — the sum of the parallel strings' currents on one input.

The details, with formulas, are in the article how many panels per string. Check a specific panel + inverter pair in the string calculator or on the panel and inverter compatibility pages.

What to check in the inverter datasheet

  • Type: grid-tie, hybrid, off-grid — whether the inverter works during an outage and whether it needs a battery.
  • Number of phases — matching the supply and the contract with the grid operator.
  • Rated AC power — how much the inverter delivers to the loads and the grid.
  • Maximum PV power — the hard limit for panel power.
  • Maximum DC input voltage — the limit for a string in frost.
  • MPPT range — the window for the string's operating voltage.
  • Number of MPPTs and strings per MPPT — how many pitches and strings you can connect.
  • Maximum input current — whether parallel strings will fit.
  • Battery class and voltage (LV/HV) — which batteries are compatible.
  • Backup output and switchover time — what will run without the grid and how fast.
  • Export limitation — whether it can run for self-consumption.

Common mistakes

  • A grid-tie inverter "for backup". It does not work without the grid — that is built into its protection.
  • Expecting a hybrid to power the whole house. In backup only the backup-output circuits run, and only within its power.
  • Buying the battery separately from the inverter. LV and HV are not interchangeable, and manufacturers list which models are compatible.
  • A single-phase inverter on a three-phase supply without a plan. Two phases will have no backup.
  • Sizing the string from the summer datasheet. The voltage in frost is higher, and that is what limits the string length.
  • Counting on export under old terms. The rules for selling energy change — check the current ones.

Frequently asked questions

How does a hybrid inverter differ from a regular grid-tie one?

A hybrid works with a battery and can power backup circuits during an outage. A grid-tie inverter shuts down without the grid because of anti-islanding protection.

Can a hybrid inverter be installed without a battery?

Yes, many models work as grid-tie inverters and a battery is added later. But how they behave without a battery in an outage depends on the model, so check the datasheet.

Which inverter to choose for a feed-in tariff?

Both grid-tie and hybrid inverters can export. The terms for selling change, so confirm the equipment and metering requirements with your grid operator before you buy.

Will an off-grid inverter suit a house with a grid connection?

Technically it can power the house, but it does not export. If the grid is there, a hybrid is usually more flexible.

How many panels can be connected to an inverter?

As many as keep you under the maximum PV power in the datasheet, with each string inside the voltage and current window of its MPPT. Check it in the string calculator.

A preliminary estimate. A qualified engineer must check it before installation.

ElectricsYield

News and design tips

What’s new in Solispec, changes to the standards and practical tips on designing solar power systems.

What interests you

How we handle your data: privacy policy.

Ground frame designer

Design the ground frame for your solar plant

Solispec picks the profiles and posts, checks the frame against snow and wind to the DBN and prices it down to the last bolt.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate