Solar plant: site data

Solar power plant in Verkhnia Rudnia, Korostenskyi Raion, Zhytomyr Oblast

Verkhnia Rudnia: 1,056 kWh per kWp a year, tilt 39° 5° east of south (PVGIS). 4.4% below the oblast median (1,104). #550 of 560 in the rayon, #1690 of 1700 in the oblast.

Korosten, the rayon centre, is 69 km away. 153 m above sea level. 69 km away: Korosten, the nearest bigger centre, 1,105 — 4.5% less here. Snow and wind from the nearest regional centre in the DBN — Житомир, 146 km. 14.36 m between rows, pitch 18.08 m (latitude 51.6°).

Yield of 1 kWp
1,056kWh/year
Tilt
39°5° east of south
10 kW
10,555kWh/year
Row pitch
18.08m · GCR 0.26
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,460 / 460Pa

Ground frame designer

A ground frame for a solar plant: Verkhnia Rudnia

The designer opens with this place’s coordinates, latitude 51.6° for the row spacing and the DBN loads of the nearest regional centre — Житомир, 146 km: snow 1,460 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

35Jan53Feb89Mar115Apr128May134Jun132Jul129Aug107Sep75Oct33Nov26Dec

June: 134 kWh/kWp, December: 26 — 5.2 times less.

October: 75 against 81 in the oblast, 7.4% less.

Verkhnia Rudnia: plants, kWh
kWpA yearJuneDecember
55,278670130
1010,5551,340260
1515,8332,010390

Snow and wind: Житомир

Example: a 10 kW ground frame

For the loads of Zhytomyr: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Korostenskyi RaionZhytomyr Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.