Solar plant: site data

Solar power plant in Rudkivka, Zhytomyrskyi Raion, Zhytomyr Oblast

Rudkivka: 1,103 kWh per kWp a year, tilt 37° 3° east of south (PVGIS). Exactly the oblast median (1,104). #535 of 686 in the rayon, #912 of 1700 in the oblast.

Zhytomyr, the rayon centre, is 26 km away. 233 m above sea level. 26 km away: Zhytomyr, the nearest bigger centre, the same 1,108. Snow and wind from the nearest regional centre in the DBN — Житомир, 25 km. 12.36 m between rows, pitch 16.18 m (latitude 50.3°).

Yield of 1 kWp
1,103kWh/year
Tilt
37°3° east of south
10 kW
11,033kWh/year
Row pitch
16.18m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,460 / 460Pa

Ground frame designer

A ground frame for a solar plant: Rudkivka

The designer opens with this place’s coordinates, latitude 50.3° for the row spacing and the DBN loads of the nearest regional centre — Житомир, 25 km: snow 1,460 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan56Feb91Mar117Apr133May139Jun139Jul135Aug110Sep82Oct36Nov30Dec

June: 139 kWh/kWp, December: 30 — 4.6 times less.

December: 30 against 27 in the oblast, 11.1% more.

Rudkivka: plants, kWh
kWpA yearJuneDecember
55,517695150
1011,0331,390300
1516,5502,085450

Snow and wind: Житомир

Example: a 10 kW ground frame

For the loads of Zhytomyr: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zhytomyrskyi RaionZhytomyr Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.