Solar power plant in Bronyky, Zviahelskyi Raion, Zhytomyr Oblast

Bronyky: 1,105 kWh per kWp a year, tilt 38° 2° east of south (PVGIS). Exactly the oblast median (1,104). #68 of 294 in the rayon, #796 of 1700 in the oblast.

Zvyahel, the rayon centre, is 15 km away. 204 m above sea level. 15 km away: Zvyahel, the nearest bigger centre, the same 1,101. Snow and wind from the nearest regional centre in the DBN — Житомир, 69 km. 12.91 m between rows, pitch 16.68 m (latitude 50.6°).

Yield of 1 kWp
1,105kWh/year
Tilt
38°2° east of south
10 kW
11,053kWh/year
Row pitch
16.68m · GCR 0.29
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,460 / 460Pa

Ground frame designer

A ground frame for a solar plant: Bronyky

The designer opens with this place’s coordinates, latitude 50.6° for the row spacing and the DBN loads of the nearest regional centre — Житомир, 69 km: snow 1,460 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan58Feb93Mar118Apr133May140Jun139Jul135Aug110Sep81Oct36Nov29Dec

June: 140 kWh/kWp, December: 29 — 4.8 times less.

December: 29 against 27 in the oblast, 7.4% more.

Bronyky: plants, kWh
kWpA yearJuneDecember
55,527700145
1011,0531,400290
1516,5802,100435

Snow and wind: Житомир

Example: a 10 kW ground frame

For the loads of Zhytomyr: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zviahelskyi RaionZhytomyr Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.