Solar plant: site data

Solar power plant in Andrushky, Zhytomyrskyi Raion, Zhytomyr Oblast

Andrushky: 1,115 kWh per kWp a year, tilt 37° 3° east of south (PVGIS). 1.0% above the oblast median (1,104). #198 of 686 in the rayon, #227 of 1700 in the oblast.

Zhytomyr, the rayon centre, is 64 km away. 202 m above sea level. 47 km away: Fastiv, the nearest bigger centre, the same 1,119. Snow and wind from the nearest regional centre in the DBN — Житомир, 64 km. 11.97 m between rows, pitch 15.79 m (latitude 49.9°).

Yield of 1 kWp
1,115kWh/year
Tilt
37°3° east of south
10 kW
11,154kWh/year
Row pitch
15.79m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,460 / 460Pa

Ground frame designer

A ground frame for a solar plant: Andrushky

The designer opens with this place’s coordinates, latitude 49.9° for the row spacing and the DBN loads of the nearest regional centre — Житомир, 64 km: snow 1,460 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

31Jan51Feb88Mar119Apr136May142Jun144Jul141Aug114Sep86Oct37Nov27Dec

July: 144 kWh/kWp, December: 27 — 5.3 times less.

February: 51 against 56 in the oblast, 8.9% less.

Andrushky: plants, kWh
kWpA yearJulyDecember
55,577720135
1011,1541,440270
1516,7312,160405

Snow and wind: Житомир

Example: a 10 kW ground frame

For the loads of Zhytomyr: 11.16 kWp, 18 panels, 350 kg of steel, 12 piles, materials ≈ 52,606 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zhytomyrskyi RaionZhytomyr Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.