Solar plant: site data
Solar power plant in Pryazovske, Melitopolskyi Raion, Zaporizhzhia Oblast
Pryazovske: 1,254 kWh per kWp a year, tilt 36° 1° west of south (PVGIS). 3.5% above the oblast median (1,212). #50 of 215 in the rayon, #81 of 972 in the oblast.
Melitopol, the rayon centre, is 24 km away. 28 m above sea level. 24 km away: Melitopol, the nearest bigger centre, 1,243 — 0.9% more here. Snow and wind from the nearest regional centre in the DBN — Запоріжжя, 129 km. 9.39 m between rows, pitch 13.26 m (latitude 46.7°).
- Yield of 1 kWp
- 1,254kWh/year
- Tilt
- 36°1° west of south
- 10 kW
- 12,537kWh/year
- Row pitch
- 13.26m · GCR 0.36
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 1,110 / 460Pa
Ground frame designer
A ground frame for a solar plant: Pryazovske
The designer opens with this place’s coordinates, latitude 46.7° for the row spacing and the DBN loads of the nearest regional centre — Запоріжжя, 129 km: snow 1,110 Pa, wind 460 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
August: 155 kWh/kWp, December: 36 — 4.3 times less.
January: 42 against 37 in the oblast, 13.5% more.
| kWp | A year | August | December |
|---|---|---|---|
| 5 | 6,269 | 775 | 180 |
| 10 | 12,537 | 1,550 | 360 |
| 15 | 18,806 | 2,325 | 540 |
Example: a 10 kW ground frame
For the loads of Zaporizhzhia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.
How these numbers are computed
Nearby
- Tavriiske5 km1,275 kWh/kWp
- Hamivka5 km1,275 kWh/kWp
- Vyshneve6 km1,259 kWh/kWp
- Novopokrovka7 km1,255 kWh/kWp
- Dobrivka8 km1,254 kWh/kWp
- Bilorichanske8 km1,275 kWh/kWp
All places: Melitopolskyi RaionZaporizhzhia Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.