Solar plant: site data

Solar power plant in Novoselivka, Polohivskyi Raion, Zaporizhzhia Oblast

Novoselivka: 1,196 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). 1.3% below the oblast median (1,212). #111 of 249 in the rayon, #676 of 972 in the oblast.

Polohy, the rayon centre, is 24 km away. 75 m above sea level. 17 km away: Orikhiv, the nearest bigger centre, 1,208 — 1.0% less here. Snow and wind from the nearest regional centre in the DBN — Запоріжжя, 69 km. 9.95 m between rows, pitch 13.82 m (latitude 47.6°).

Yield of 1 kWp
1,196kWh/year
Tilt
36°2° east of south
10 kW
11,955kWh/year
Row pitch
13.82m · GCR 0.35
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
1,110 / 460Pa

Ground frame designer

A ground frame for a solar plant: Novoselivka

The designer opens with this place’s coordinates, latitude 47.6° for the row spacing and the DBN loads of the nearest regional centre — Запоріжжя, 69 km: snow 1,110 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan55Feb98Mar119Apr140May142Jun150Jul151Aug125Sep95Oct52Nov31Dec

August: 151 kWh/kWp, December: 31 — 4.9 times less.

November: 52 against 54 in the oblast, 3.7% less.

Novoselivka: plants, kWh
kWpA yearAugustDecember
55,978755155
1011,9551,510310
1517,9332,265465

Snow and wind: Запоріжжя

Example: a 10 kW ground frame

For the loads of Zaporizhzhia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Polohivskyi RaionZaporizhzhia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.