Solar plant: site data

Solar power plant in Mokryi Stav, Berdianskyi Raion, Zaporizhzhia Oblast

Mokryi Stav: 1,216 kWh per kWp a year, tilt 36° 1° east of south (PVGIS). Exactly the oblast median (1,212). #75 of 116 in the rayon, #394 of 972 in the oblast.

Berdyansk, the rayon centre, is 70 km away. 108 m above sea level. 41 km away: Polohy, the nearest bigger centre, 1,199 — 1.4% more here. Snow and wind from the nearest regional centre in the DBN — Запоріжжя, 104 km. 9.64 m between rows, pitch 13.51 m (latitude 47.1°).

Yield of 1 kWp
1,216kWh/year
Tilt
36°1° east of south
10 kW
12,164kWh/year
Row pitch
13.51m · GCR 0.35
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
1,110 / 460Pa

Ground frame designer

A ground frame for a solar plant: Mokryi Stav

The designer opens with this place’s coordinates, latitude 47.1° for the row spacing and the DBN loads of the nearest regional centre — Запоріжжя, 104 km: snow 1,110 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

39Jan57Feb99Mar121Apr141May141Jun151Jul152Aug127Sep98Oct57Nov33Dec

August: 152 kWh/kWp, December: 33 — 4.6 times less.

November: 57 against 54 in the oblast, 5.6% more.

Mokryi Stav: plants, kWh
kWpA yearAugustDecember
56,082760165
1012,1641,520330
1518,2462,280495

Snow and wind: Запоріжжя

Example: a 10 kW ground frame

For the loads of Zaporizhzhia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Berdianskyi RaionZaporizhzhia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.