Solar plant: site data
Solar power plant in Torkiv, Tulchynskyi Raion, Vinnytsia Oblast
Torkiv: 1,146 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). Exactly the oblast median (1,143). #169 of 184 in the rayon, #516 of 1206 in the oblast.
Tulchyn, the rayon centre, is 16 km away. 233 m above sea level. 16 km away: Tulchyn, the nearest bigger centre, 1,156 — 0.8% less here. Snow and wind from the nearest regional centre in the DBN — Вінниця, 54 km. 10.77 m between rows, pitch 14.64 m (latitude 48.8°).
- Yield of 1 kWp
- 1,146kWh/year
- Tilt
- 36°2° east of south
- 10 kW
- 11,461kWh/year
- Row pitch
- 14.64m · GCR 0.33
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,360 / 470Pa
Ground frame designer
A ground frame for a solar plant: Torkiv
The designer opens with this place’s coordinates, latitude 48.8° for the row spacing and the DBN loads of the nearest regional centre — Вінниця, 54 km: snow 1,360 Pa, wind 470 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 144 kWh/kWp, January: 36 — 4.0 times less.
December: 36 against 32 in the oblast, 12.5% more.
| kWp | A year | July | January |
|---|---|---|---|
| 5 | 5,731 | 720 | 180 |
| 10 | 11,461 | 1,440 | 360 |
| 15 | 17,192 | 2,160 | 540 |
Example: a 10 kW ground frame
For the loads of Vinnytsia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.
How these numbers are computed
Nearby
- Petrashivka4 km1,147 kWh/kWp
- Shpykivka5 km1,148 kWh/kWp
- Silnytsia6 km1,153 kWh/kWp
- Kopiivka7 km1,148 kWh/kWp
- Bortnyky8 km1,146 kWh/kWp
- Sosnivka8 km1,148 kWh/kWp
All places: Tulchynskyi RaionVinnytsia Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.