Solar plant: site data
Solar power plant in Petrashivka, Mohyliv-Podilskyi Raion, Vinnytsia Oblast
Petrashivka: 1,150 kWh per kWp a year, tilt 36° 10° east of south (PVGIS). 0.6% above the oblast median (1,143). #111 of 158 in the rayon, #389 of 1206 in the oblast.
Mohyliv-Podilskyy, the rayon centre, is 31 km away. 86 m above sea level. 31 km away: Mohyliv-Podilskyy, the nearest bigger centre, 1,160 — 0.9% less here. Snow and wind from the nearest regional centre in the DBN — Вінниця, 106 km. 10.42 m between rows, pitch 14.29 m (latitude 48.3°).
- Yield of 1 kWp
- 1,150kWh/year
- Tilt
- 36°10° east of south
- 10 kW
- 11,496kWh/year
- Row pitch
- 14.29m · GCR 0.33
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 1,360 / 470Pa
Ground frame designer
A ground frame for a solar plant: Petrashivka
The designer opens with this place’s coordinates, latitude 48.3° for the row spacing and the DBN loads of the nearest regional centre — Вінниця, 106 km: snow 1,360 Pa, wind 470 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 147 kWh/kWp, December: 33 — 4.5 times less.
February: 49 against 52 in the oblast, 5.8% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,748 | 735 | 165 |
| 10 | 11,496 | 1,470 | 330 |
| 15 | 17,244 | 2,205 | 495 |
Example: a 10 kW ground frame
For the loads of Vinnytsia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.
How these numbers are computed
Nearby
- Myronivka1 km1,167 kWh/kWp
- Khmelivshchyna5 km1,164 kWh/kWp
- Doroshivka5 km1,164 kWh/kWp
- Derzhanka5 km1,165 kWh/kWp
- Busha5 km1,163 kWh/kWp
- Mykhailivka6 km1,167 kWh/kWp
All places: Mohyliv-Podilskyi RaionVinnytsia Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.