Solar plant: site data

Solar power plant in Maiaky, Tulchynskyi Raion, Vinnytsia Oblast

Maiaky: 1,162 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 1.7% above the oblast median (1,143). #42 of 184 in the rayon, #99 of 1206 in the oblast.

Tulchyn, the rayon centre, is 13 km away. 309 m above sea level. 13 km away: Tulchyn, the nearest bigger centre, 1,156 — 0.5% more here. Snow and wind from the nearest regional centre in the DBN — Вінниця, 72 km. 10.90 m between rows, pitch 14.72 m (latitude 48.6°).

Yield of 1 kWp
1,162kWh/year
Tilt
37°2° east of south
10 kW
11,618kWh/year
Row pitch
14.72m · GCR 0.33
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,360 / 470Pa

Ground frame designer

A ground frame for a solar plant: Maiaky

The designer opens with this place’s coordinates, latitude 48.6° for the row spacing and the DBN loads of the nearest regional centre — Вінниця, 72 km: snow 1,360 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

38Jan54Feb97Mar121Apr139May140Jun144Jul142Aug118Sep90Oct44Nov35Dec

July: 144 kWh/kWp, December: 35 — 4.1 times less.

December: 35 against 32 in the oblast, 9.4% more.

Maiaky: plants, kWh
kWpA yearJulyDecember
55,809720175
1011,6181,440350
1517,4272,160525

Snow and wind: Вінниця

Example: a 10 kW ground frame

For the loads of Vinnytsia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Tulchynskyi RaionVinnytsia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.