Solar plant: site data

Solar power plant in Oryshkivtsi, Chortkivskyi Raion, Ternopil Oblast

Oryshkivtsi: 1,124 kWh per kWp a year, tilt 37° 1° east of south (PVGIS). 2.8% above the oblast median (1,093). #72 of 296 in the rayon, #72 of 744 in the oblast.

Chortkiv, the rayon centre, is 8 km away. 302 m above sea level. 8 km away: Chortkiv, the nearest bigger centre, the same 1,126. Snow and wind from the nearest regional centre in the DBN — Тернопіль, 57 km. 11.27 m between rows, pitch 15.09 m (latitude 49.1°).

Yield of 1 kWp
1,124kWh/year
Tilt
37°1° east of south
10 kW
11,235kWh/year
Row pitch
15.09m · GCR 0.32
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,390 / 520Pa

Ground frame designer

A ground frame for a solar plant: Oryshkivtsi

The designer opens with this place’s coordinates, latitude 49.1° for the row spacing and the DBN loads of the nearest regional centre — Тернопіль, 57 km: snow 1,390 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

39Jan57Feb96Mar118Apr132May134Jun139Jul136Aug112Sep86Oct40Nov34Dec

July: 139 kWh/kWp, December: 34 — 4.1 times less.

January: 39 against 34 in the oblast, 14.7% more.

Oryshkivtsi: plants, kWh
kWpA yearJulyDecember
55,618695170
1011,2351,390340
1516,8532,085510

Snow and wind: Тернопіль

Example: a 10 kW ground frame

For the loads of Ternopil: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Chortkivskyi RaionTernopil Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.