Solar plant: site data
Solar power plant in Kryvche, Chortkivskyi Raion, Ternopil Oblast
Kryvche: 1,126 kWh per kWp a year, tilt 37° facing south (PVGIS). 3.1% above the oblast median (1,093). #44 of 296 in the rayon, #44 of 744 in the oblast.
Chortkiv, the rayon centre, is 42 km away. 228 m above sea level. 28 km away: Zastavna, the nearest bigger centre, the same 1,131. Snow and wind from the nearest regional centre in the DBN — Чернівці, 47 km. 10.98 m between rows, pitch 14.80 m (latitude 48.7°).
- Yield of 1 kWp
- 1,126kWh/year
- Tilt
- 37°facing south
- 10 kW
- 11,262kWh/year
- Row pitch
- 14.80m · GCR 0.32
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,320 / 500Pa
Ground frame designer
A ground frame for a solar plant: Kryvche
The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Чернівці, 47 km: snow 1,320 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 140 kWh/kWp, December: 34 — 4.1 times less.
January: 41 against 34 in the oblast, 20.6% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,631 | 700 | 170 |
| 10 | 11,262 | 1,400 | 340 |
| 15 | 16,893 | 2,100 | 510 |
Example: a 10 kW ground frame
For the loads of Chernivtsi: 11.16 kWp, 18 panels, 412 kg of steel, 16 piles, materials ≈ 54,638 UAH.
How these numbers are computed
Nearby
- Sapohiv4 km1,132 kWh/kWp
- Khudiivtsi5 km1,109 kWh/kWp
- Babyntsi5 km1,103 kWh/kWp
- Hermakivka5 km1,128 kWh/kWp
- Shyshkivtsi6 km1,130 kWh/kWp
- Skoviatyn6 km1,131 kWh/kWp
All places: Chortkivskyi RaionTernopil Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.