Solar plant: site data

Solar power plant in Koziari, Ternopilskyi Raion, Ternopil Oblast

Koziari: 1,084 kWh per kWp a year, tilt 36° 1° east of south (PVGIS). 0.7% below the oblast median (1,093). #173 of 313 in the rayon, #512 of 744 in the oblast.

Ternopil, the rayon centre, is 37 km away. 304 m above sea level. 13 km away: Pidvolochysk, the nearest bigger centre, the same 1,089. Snow and wind from the nearest regional centre in the DBN — Тернопіль, 37 km. 11.48 m between rows, pitch 15.35 m (latitude 49.6°).

Yield of 1 kWp
1,084kWh/year
Tilt
36°1° east of south
10 kW
10,844kWh/year
Row pitch
15.35m · GCR 0.31
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,390 / 520Pa

Ground frame designer

A ground frame for a solar plant: Koziari

The designer opens with this place’s coordinates, latitude 49.6° for the row spacing and the DBN loads of the nearest regional centre — Тернопіль, 37 km: snow 1,390 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

28Jan46Feb85Mar117Apr134May136Jun140Jul137Aug112Sep84Oct37Nov29Dec

July: 140 kWh/kWp, January: 28 — 5.0 times less.

January: 28 against 34 in the oblast, 17.6% less.

Koziari: plants, kWh
kWpA yearJulyJanuary
55,422700140
1010,8441,400280
1516,2662,100420

Snow and wind: Тернопіль

Example: a 10 kW ground frame

For the loads of Ternopil: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Ternopilskyi RaionTernopil Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.