Solar plant: site data

Solar power plant in Korolivka, Chortkivskyi Raion, Ternopil Oblast

Korolivka: 1,115 kWh per kWp a year, tilt 36° 7° east of south (PVGIS). 2.1% above the oblast median (1,093). #166 of 296 in the rayon, #166 of 744 in the oblast.

Chortkiv, the rayon centre, is 34 km away. 186 m above sea level. 27 km away: Zastavna, the nearest bigger centre, 1,131 — 1.4% less here. Snow and wind from the nearest regional centre in the DBN — Чернівці, 50 km. 10.75 m between rows, pitch 14.62 m (latitude 48.7°).

Yield of 1 kWp
1,115kWh/year
Tilt
36°7° east of south
10 kW
11,150kWh/year
Row pitch
14.62m · GCR 0.33
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,320 / 500Pa

Ground frame designer

A ground frame for a solar plant: Korolivka

The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Чернівці, 50 km: snow 1,320 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

39Jan54Feb95Mar118Apr133May133Jun141Jul136Aug113Sep84Oct39Nov30Dec

July: 141 kWh/kWp, December: 30 — 4.7 times less.

January: 39 against 34 in the oblast, 14.7% more.

Korolivka: plants, kWh
kWpA yearJulyDecember
55,575705150
1011,1501,410300
1516,7252,115450

Snow and wind: Чернівці

Example: a 10 kW ground frame

For the loads of Chernivtsi: 11.16 kWp, 18 panels, 412 kg of steel, 16 piles, materials ≈ 54,638 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Chortkivskyi RaionTernopil Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.