Solar plant: site data

Solar power plant in Chekhiv, Chortkivskyi Raion, Ternopil Oblast

Chekhiv: 1,102 kWh per kWp a year, tilt 37° 2° west of south (PVGIS). 0.8% above the oblast median (1,093). #270 of 296 in the rayon, #284 of 744 in the oblast.

Chortkiv, the rayon centre, is 44 km away. 306 m above sea level. 22 km away: Pidhaytsi, the nearest bigger centre, 1,094 — 0.7% more here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 40 km. 11.27 m between rows, pitch 15.09 m (latitude 49.1°).

Yield of 1 kWp
1,102kWh/year
Tilt
37°2° west of south
10 kW
11,015kWh/year
Row pitch
15.09m · GCR 0.32
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,410 / 500Pa

Ground frame designer

A ground frame for a solar plant: Chekhiv

The designer opens with this place’s coordinates, latitude 49.1° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 40 km: snow 1,410 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan54Feb96Mar116Apr128May128Jun137Jul135Aug111Sep86Oct41Nov32Dec

July: 137 kWh/kWp, December: 32 — 4.3 times less.

January: 37 against 34 in the oblast, 8.8% more.

Chekhiv: plants, kWh
kWpA yearJulyDecember
55,508685160
1011,0151,370320
1516,5232,055480

Snow and wind: Івано-Франківськ

Example: a 10 kW ground frame

For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Chortkivskyi RaionTernopil Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.