Solar plant: site data

Solar power plant in Shalyhyne, Shostkynskyi Raion, Sumy Oblast

Shalyhyne: 1,099 kWh per kWp a year, tilt 38° 1° east of south (PVGIS). 0.9% below the oblast median (1,110). #68 of 258 in the rayon, #1229 of 1534 in the oblast.

Shostka, the rayon centre, is 56 km away. 185 m above sea level. 56 km away: Shostka, the nearest bigger centre, 1,082 — 1.7% more here. Snow and wind from the nearest regional centre in the DBN — Суми, 87 km. 14.06 m between rows, pitch 17.83 m (latitude 51.6°).

Yield of 1 kWp
1,099kWh/year
Tilt
38°1° east of south
10 kW
10,994kWh/year
Row pitch
17.83m · GCR 0.27
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,670 / 420Pa

Ground frame designer

A ground frame for a solar plant: Shalyhyne

The designer opens with this place’s coordinates, latitude 51.6° for the row spacing and the DBN loads of the nearest regional centre — Суми, 87 km: snow 1,670 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan60Feb95Mar115Apr139May142Jun141Jul138Aug107Sep72Oct33Nov22Dec

June: 142 kWh/kWp, December: 22 — 6.5 times less.

November: 33 against 35 in the oblast, 5.7% less.

Shalyhyne: plants, kWh
kWpA yearJuneDecember
55,497710110
1010,9941,420220
1516,4912,130330

Snow and wind: Суми

Example: a 10 kW ground frame

For the loads of Sumy: 11.16 kWp, 18 panels, 385 kg of steel, 12 piles, materials ≈ 51,876 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Shostkynskyi RaionSumy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.