Solar plant: site data

Solar power plant in Chernetske, Sumskyi Raion, Sumy Oblast

Chernetske: 1,126 kWh per kWp a year, tilt 38° 2° east of south (PVGIS). 1.5% above the oblast median (1,110). #23 of 466 in the rayon, #204 of 1534 in the oblast.

Sumy, the rayon centre, is 11 km away. 162 m above sea level. 11 km away: Sumy, the nearest bigger centre, 1,117 — 0.8% more here. Snow and wind from the nearest regional centre in the DBN — Суми, 10 km. 13.27 m between rows, pitch 17.04 m (latitude 50.9°).

Yield of 1 kWp
1,126kWh/year
Tilt
38°2° east of south
10 kW
11,261kWh/year
Row pitch
17.04m · GCR 0.28
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,670 / 420Pa

Ground frame designer

A ground frame for a solar plant: Chernetske

The designer opens with this place’s coordinates, latitude 50.9° for the row spacing and the DBN loads of the nearest regional centre — Суми, 10 km: snow 1,670 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

38Jan64Feb99Mar115Apr139May142Jun143Jul141Aug109Sep76Oct36Nov24Dec

July: 143 kWh/kWp, December: 24 — 6.0 times less.

February: 64 against 59 in the oblast, 8.5% more.

Chernetske: plants, kWh
kWpA yearJulyDecember
55,631715120
1011,2611,430240
1516,8922,145360

Snow and wind: Суми

Example: a 10 kW ground frame

For the loads of Sumy: 11.16 kWp, 18 panels, 385 kg of steel, 12 piles, materials ≈ 51,876 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Sumskyi RaionSumy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.